Cable Laying at “Rafael Urdaneta” Bridge. Maracaibo Lake

Name of Contract: Interconexion Cadafe – Enelven . Cable de Aceite de 230 KV

Client: Sumitomo / Cadafe

Scope of Work and Location: Cable Laying at “Rafael Urdaneta” Bridge. Interconnection Cadafe - Enelven, Oil Cable of 230 KV. Maracaibo Lake, State Zulia.

Duration and Man Hours: 1 Year, 240.000 MH Aprox.

Amount $ (USD): Aprox. $ 2.209.302,00

 

Poliducto Ø8”. 200 Km. SISOR Project. Section No. 4 San Tome – Maturín

Name of Contract: Proyecto SISOR. Tendido de Tubería del Poliducto Planta San Tome – Planta Maturín.
Client: Meneven (Filial PDVSA)
Date: 1986
Scope of Work and Location: Construction and installation of poliducto of 158 Km. of Ø 8" between the State Anzoategui and Monagas
Duration and Man Hours: 6 Months, 280.000 HH Aprox.
Amount $ (USD): Aprox. $ 1.785.114.979,00

  Go up
 

Modules Fabrication and Installation Gas Compression Boostgas

Name of Contract: Construcción e Instalación De Boostgas Bloque V Y III
Client: Turbina Solar
Date: 1992
Scope of Work and Location: Fabrication and Installation of Four Modules of 460 Ton each one for the Gas Compression Plant. Yard Flag Ciudad Ojeda City. Zulia State
Duration and Man Hours: Seven Months
mount $ (USD): Aprox. $ 7.359.113,59

  Go up
 

Pipeline 17 Km. Ø 26”. Muscar - Sta. Barbara.

Name of Contract: Tendido de 17 Km. Gasducto Ø 26" desde Muscar hasta Sta. Barbara
Client: Corpoven (Filial PDVSA)
Date: 1995
Scope of Work and Location: Construction and installation of gas pipeline of 17 Km. of Ø26" from Muscar to Santa Barbara. Monagas State
Duration and Man Hours: Five Months. 100.000 MH
Amount $ (USD): Aprox. $ 1.876.612.425,00

  Go up
 

Off Shore Hook-Up, Central Facilities Complex Chevron LL-652

Name of Contract:LL-652 Development Project - Offshore Hook-Up and commissioning support central facility complex
Client: Bechtel
Date: 1999
Scope of Work and Location: Hook up and Commissioning of 5000 Ton platform. (Main production platform. Water Injection platform, Power generation platform) previously built in USA. Maracaibo Lake, Zulia State.
Duration and Man Hours: Three Months
Amount $ (USD): Aprox. $ 7.484.766,00

  Go up
 

Construction of LAMA III Plant

Name of Contract: Construcción de Planta LAMA III
Client: Turbina solar / JANSA
Date: 1992
Scope of Work and Location: Installation of Gas Compressors in the Maracaibo Lake.
Duration and Man Hours: twelve months and half
Amount $ (USD): Aprox. $ 3.762.618,00

  Go up
 

Maraven of Refinery Project of Expansion -Cardon

Name of Contract: Proyecto de Expansion de Refineria Cardon
Client: Bechtel / Maraven
Date: 1993
Scope of Work: Modules Fabrication of 250 Ton. Aprox. Patio Flag , Falg Yard Maracaibo, Edo Zulia
Duration and Man Hours: twelve months
Amount $ (USD): Aprox. $ 5.085.745,28

  Go up
 

Fabrication and Installation of Offshore Topsides Modules. Maracaibo Lake.

Name of Contract: Fabrication and Installation of Offshore Topsides Modules. Maracaibo Lake.
Client: Shell Venezuela
Date: 1996
Alcance General y Localizacion / Scope of Work and Location: Engineering of Field and Shop Drawing. Manufacture of Offshore Platforms. Load out and offshore transportation on trough cargo barge of units up to 500 Topside ton Interconnection, test commissioning and hand hover of systems. Supply of personnel for the start up. Total : 3.000 Ton.
Duration and Man Hours: twelve Months
Amount $ (USD): Aprox. $ 6.027.716,93

  Go up
 

Engeneering Procurement and Construction of Facilities production (70.000 BLS / day). Pedernales Delta Amacuro

Name of Contract: Installation of pipelines and marine related facilities. Proyecto BP-Pedernales Fase II
Client: BP – Exploracion / PDVSA
Date: 1997
Scope of Work and Location: Engeneering Procurement and Construction altogether with CBS Bay Offshore Mcdermoth Gulf Island Fabricators and Jantesa. Provision of pipes of 3", painting, electrical equipments and instrumentation. Manufacture of Jackets, platform, Bridges (Total 5000 ton) Interconnection in site of Jackets, FSPP and Bridges. Commisioning and Hand over. Yards FLAG in Maracaibo, Barcelona and Guira.
Amount $ (USD): Aprox. $ 18.000.000.000

  Go up
 

Offshore Accomodation Development Project

Name of Contract: Offshore Accomodation Development Project
Client: Shell Venezuela
Date: 2000
Scope of Work and Location: Engineering of Field and Shop Drawing. Manufacture of Offshore Platforms. Load out and offshore transportation on trough cargo barge of units up to 500 ton Topside Interconnection, test commissioning and hand hover of systems. Supply of personnel for the start up. Yard FLAG, Maracaibo and Maracibo Lake, Edo. Zulia.
Duration and Man Hours: Three months
Amount $ (USD): Aprox. $ 1.356.378,0

  Go up
 

Modules Fabrication for Exportation

Name of Contract: Fabricación de Módulos Proyecto “HOVENSA Delayed Coker”
Client: Bechtel
Date: 2000
Scope of Work and Location: Manufacture of piperack and process modules up to 300 ton. Field Engeneering and shop drawing, Load out and sea fastening. Maracaibo Zulia State.
Duration and Man Hours: Twelve months
Amount $ (USD): Aprox. $ 22.395.967,58

  Go up
 

Topsides Fabrication, Manifold Platform Topsides, LL-652 Development Project. C4 Project Well Head Platform

Name of Contract: Standing Contract for Topsides Fabrication, Manifold Platform Topsides, LL-652 Development Project. C4 Project Well Head Platform
Client: Chevron
Date: 2000
Scope of Work and Location: Fabrication, Installation and Comissioning of offshore platform (C4 y N1)
Duration and Man Hours: Six months
Amount $ (USD): Aprox. $ 7.861.500,13

  Go up
 

TAEJ Project Bottom Pull of 36” and 20”

Name of Contract: Tendido de Línea Costa Afuera de tubería de Ø36” y 20” en el terminal de JOSE / Offshore Line Laying pipe Ø36 "and 20" in the terminal JOSE
Client: CAMSA - WILBROS
Date: 2003 – 2004
Scope of Work and Location: Pulling and laying of 6 km of pipe 36 "and 6 km of pipe 20"
Duration and Man Hours: Six months. 200.000 MH
Amount $ (USD): Aprox. $ 11.500.000

  Go up
 

WORKS Campo Boscan Electrical, Mechanical, Erection. Flow Station Z-9 (Capacidad: 100.000 BLS)

Client: Chevron

  Go up
 

Compressor Plant Gas (Oriente)

Client: Repsol

  Go up
 

Facilities Production

Client: Shell de Venezuela

  Go up
 

Pipeline Ø 20”. 12 Km. Morichal

Client: PDVSA

  Go up
 

TAEJ Project Bottom Pull of 36” and 20” Pipeline

Client: WILBROS - CAMSA

  Go up
 

Pipe Laying Ø20”, 20 Km. Gulf of Coro

Client: PDVSA

  Go up
 

Pipe Laying 40 Km. Ø16”. Pedernales

Client: British Petroleum

  Go up
 
 
Executed Works
Cable Laying at “Rafael Urdaneta” Bridge.
Poliducto Ø8”. 200 Km. SISOR Project. Section No. 4
Modules Fabrication and Installation Gas Compression
Pipeline 17 Km. Ø 26”. Muscar
Offshore Hook-Up, Central Facilities Complex Chevron LL-652
Construction of LAMA III Plant
Maraven of Refinery Project of Expansion
Fabrication and Installation of Offshore Topsides Modules
Engeneering Procurement and Construction of Facilities production (70.000 BLS / day)
Offshore Accomodation Development Project
Modules Fabrication for Exportation
Topsides Fabrication, Manifold Platform Topsides, LL-652
Pipe Laying
WORKS Campo Boscan Electrical, Mechanical, Erection. Flow Station Z-9 (Capacidad: 100.000 BLS)
Compressor Plant Gas (Oriente)
Facilities Production
Pipeline Ø 20”. 12 Km. Morichal
TAEJ Project Bottom Pull of 36” and 20” Pipeline
Pipe Laying Ø20”, 20 Km. Gulf of Coro
Pipe Laying 40 Km. Ø16”. Pedernales
 
 
 
       
  Flag Instalaciones, S.A 2021 © Av. 22 con Calle 70, C.C. Taicupa, Local 24, Maracaibo, Venezuela.
Teléfonos: +58 261 7526472 / 2011265 / 2011266
Correo Electrónico: info@flag.com.ve